img
logo

What is the Planned Value Control Option

It is a system that controls the output to achieve the planned simultaneous and equal amount required for self-consignment. It also supports output curtailment by the transmission and distribution operators, allowing the simultaneous use of planned value control and output curtailment.

What is self-consignment

Self-consignment is a system in which electricity generated from a power generation facility is transmitted (consigned) to other locations via the power grid.


What is Planned Simultaneous and Equal Amount?

When using self-consignment, it is required to match the planned values with the actual values.

img01
img02

※For information on supported Inverter manufacturers, please contact your sales representative.
※Please note that customers are responsible for forecasting power generation, creating various plans required for self-consignment, and submitting them to OCCTO.

Function Overview

1Planned Value Control

The measurement device controls the Inverter based on the power generation planned values created by the customer. It also supports output curtailment by transmission and distribution operators, allowing the simultaneous use of planned value control and output curtailment.

ZERO-T4

Measurement Device:
Solar Link ZERO

A compact measurement and control terminal that measures and records the power generation status in real-time and
uploads the data to the server.
It also performs output curtailment of the Inverter.

※Please note that this system does not guarantee the exact matching of the planned and actual power generation values.
※If the power company applies output curtailment separately, the system may prioritize the output curtailment operations.

img03

2Uploading Planned Values

Manual Upload

Set the target date and upload a CSV file created according to our specified format*.
* The file should contain the power generation plan in 30-minute intervals (kWh) for one day (48 time slots) in a single file.

img04 img04-2

Uploading via Web API

Using the Web API provided by our company, you can automatically upload the planned values.
※To enable automatic uploading, you will need to prepare a program for uploading the planned values.
※A non-disclosure agreement (NDA) is required for use. After the contract is signed, the API specification document will be provided.
※For more details on the specifications, please consult with your sales representative.

3Check Power Generation Results and Plans

After selecting the year, month, and day, you can check the planned values and actual values from each button.

img05

CSV Download

You can export the planned values, actual values, deviation rates, and output curtailment measurement items for the specified day (1 day) at 30-minute intervals in CSV format.

Graph and Report Display

The planned values and actual values are displayed in a graph. The report shows the planned values, actual values, and deviation rates.

Update

Update the display content of the graph and report.
※You need to manually update the graph and report display content.

4Plan Update History

Displays up to 10,000 records of past history from the selected date.

img06

※ A maximum of 100 records per page.